Adams and Washington Streets are closed starting TODAY, June 25th, 2025 for approximately five days, and inner lane restrictions are in place on SR 18 E and W. Crews were able to start sooner than planned around the Courthouse Square for bricks to be replaced with asphalt in accordance with Indiana Department of Transportation specifications.
Phase #1:
Road Closures:
- Adams St. between SR18 E and W
- Washington St. between SR18 E and W
This will be the inside portion around the Courthouse Square. Phase #1 will take approximately five days beginning WEDNESDAY, June 25th. When Phase #1 is complete, Phase #2 will start.
Phase #2:
Lane Closures:
- SR 18 E and W (outer lanes of the Courthouse Square)
This phase will take approximately five days to complete.
*Detour signs and lane closures will be placed.
*No parking is permitted in this area during the demolition and construction.